Tech Company Toronto Headquarters Furniture & Workplace Delivery
A technology company was opening its first office outside of the United States, establishing a new Toronto workplace for approximately 50 employees operating within a hybrid work model.

The project brought together a complex mix of workplace environments including executive and open work areas, meeting rooms, a town hall, kitchen, phone booths, lockers, and integrated planting while maintaining a cohesive design language established by the interior design team.
As the furniture dealer, FF&E specialist, and project manager, the challenge extended beyond selecting furniture. The project required translating the design intent into a coordinated procurement and installation strategy while navigating tight lead times, multiple vendors, building requirements, and a fixed opening date.
The critical question became: How can a complex furniture package move from design concept to fully installed workplace without compromising the design, schedule, or client experience?
The approach centered on early coordination, transparent communication, and proactive project management.
The interior design team's mood board and design intent were reviewed to establish the functional and aesthetic requirements of the furniture package. Product options were then developed around those requirements, balancing design, availability, lead times, budget, and installation logistics.

Because lead times represented the project's greatest risk, furniture procurement was treated as an integrated part of the construction schedule rather than a separate purchasing exercise.
A centralized project-management system was developed in Asana to connect specification, purchasing, delivery, installation, documentation, and project milestones. This created a single operational view of the furniture scope and allowed potential issues to be identified and communicated before they became installation or schedule problems.
Communication became a key part of the strategy. With a large group of stakeholders involved, consistent updates and clear explanations around decisions, timelines, and changes helped create alignment and reduce uncertainty throughout the project.
The project began with a detailed review of the design direction, followed by furniture specifications, finish selections, budgeting, and lead-time analysis. Furniture and installation budgets were developed to establish cost visibility early in the process, while product selections were evaluated against both the design intent and procurement realities.
Once the project was approved, the furniture scope moved into execution across approximately 7 vendors, and a 10-person installation crew, alongside coordination with AV and the general contractor.
Approximately 10 purchase orders were managed throughout procurement, with estimates and invoices submitted and tracked as the project progressed.
A project tracker built in Asana provided visibility across orders, vendors, deliveries, installation requirements, and outstanding items. Project timelines were developed to coordinate furniture procurement with construction and building schedules, while required documentation was prepared and submitted to building management for approvals.

Coordination with the interior designer and general contractor was maintained primarily through email and virtual meetings, ensuring that furniture decisions remained aligned with the broader construction and design process.
Installation was planned around the client's operational needs. While the majority of the furniture was delivered and installed in time for the office opening, a small number of items were strategically moved into a Phase 2 after-hours installation to avoid disrupting the client's team.
The office opened on schedule, despite the project's lead-time and coordination challenges.
The completed workplace successfully brought the design vision into a functional environment for a 50-person hybrid workforce, while maintaining alignment across design, procurement, construction, and installation.
The project demonstrated the value of treating FF&E delivery as a strategic project-management function rather than a final-stage purchasing exercise.
Key outcomes included:
On-time office opening despite significant lead-time constraints
Coordination across 7+ vendors and multiple project partners
Management of approximately 15 purchase orders
Coordination of a 10-person installation team
Integration of furniture delivery with construction and building requirements
Phased after-hours installation to minimize disruption to the client
Centralized project tracking through Asana
Continuous stakeholder communication throughout procurement and installation
Most significantly, the success of the project extended beyond the initial delivery. Following completion, the client re-engaged the team for the company's expansion phase.